What are the different methods of ranking of projects?


Ans.  Two approaches are available for determining which project to accept and which projects to reject : (i) the method of ranking, and (ii) the method of mathematical programming.This section discusses the method of ranking ; the following section discusses the method of mathematical programming.
The method of ranking consists of two steps : (i) Rank all projects in a decreasing order according to their individual NPV’s, IRR’s or BCR’s. (ii) Accept project in that order until the capital budget is exhausted. The method of ranking, originally proposed by Joel Dean is seriously impaired by two problems: (i) conflict in ranking as per discounted cash flow criteria, and (ii)project indivisibility.
Conflict in Ranking
In a given set of projects, preference ranking tends to differ from one criterion to another. For example, NPV and IRR criteria may yield different preference rankings. Likewise, there may be a discrepancy between the preference rankings of NPV and BCR (benefit cost ratio) criteria. When preference rankings differ, the set of projects selected as per one criterion tends to differ from the set of projects selected as per some other criterion. This may be illustrated by an example. Consider a set of five projects, A, B, C, D, and E, for which the investment
outlay, expected annual cash flow, and project life are as shown below:
Project                            Investment outlay                     Expected annual         Project life
                                                                                                cash flow
                                                     (Rs)                                       (Rs)                        (Years)
A                                                  10,000                                  4,000                           12
B                                                   25,000                                 10,000                          4
C                                                   30,000                                  6,000                           20
D                                                   38,000                                 12,000                          16
E                                                    35,000                                 12,000                          9

The NPV, IRR and BCR for the five projects and the ranking along these dimensions
are shown  below
 NPV, IRR and BCR for the Five Projects
Project                              NPV          NPV           IRR             IRR          BCR            BCR
(Rs)                                                  Ranking  (Per cent)     Ranking                   Ranking
A                                        14,776       4              39                 1             2.48            1
B                                      5,370        5                          22              4           1.21            5
C                                            14,814       3             19                5             1.49            4
D                                            45,688       1             30                2              2.20           2
E                                             28,936      2             29                3              1.83           3
It is clear that in the above case the three criteria rank the projects differently. If there is no capital rationing, all the projects would be accepted under all the three criteria though internal ranking may differ across criteria. However, if the funds available are limited, the set of projects accepted would depend on the criterion adopted. What causes ranking conflicts? Ranking conflicts are traceable to differing assumptions made about the rate of return at which intermediate cash flows are re-invested.

Project Indivisibility
A problem in choosing the capital budget on the basis of individual ranking arises because of indivisibility of capital expenditure projects. To illustrate, consider the following set of projects (ranked according to their NPV) being evaluated by a firm which has a capital budget constraint of Rs. 2,500, 000.
Project                                                           Outlay                           NPV
                                                                          Rs.                               Rs.
A                                                                   1,500,000                    400,000
B                                                                   1,000,000                    350,000
C                                                                    800,000                      300,000
D                                                                   700,000                       300,000
E                                                                    600,000                       250,000

If the selection is based on individual NPV ranking, projects A and B would be included in the capital budget- these projects exhaust the capital budget. A cursory examination, however, would suggest that it is more desirable to select projectsB, C, and D. These three projects can be accommodated within the capital budget of Rs. 2,500,000, and have a combined  NPV of Rs. 850,000, which is greater than the combined NPV of projects A and B.
Feasible Combinations Approach
The above example suggests that the following procedure may be used for selecting the set of investments under capital rationing. 1. Define all combinations of projects which are feasible, given the capital budget restriction and project interdependencies.
2. Choose the feasible combination that has the highest NPV. To illustrate this procedure, consider the following projects that are being evaluated by a firm which has a capital budget constraint of Rs. 3,000,000.
Project Outlay NPV
                         Rs.                               Rs.
A                  1,800,000                   750,000
B                  1,500,000                   600,000
C                  1,200,000                   500,000
D                  750,000                      360,000
E                  600,000                      300,000
Projects B and C are mutually exclusive. Other projects are independent Given the above information the feasible combinations and their NPV are shown below:
Feasible Outlay NPV combination
                           Rs.                                   Rs.
A                   1,800,000                        750,000
B                   1,500,000                        600,000
C                   1,200,000                        500,000
D                   750,000                           360,000
E                    600,000                          300,000
A and C        3,000,000                       1,250,000
A and D        2,550,000                      1,110,000
A and E         2,400,000                      1,050,000
B and D        2,250,000                       960,000
B and E         2,100,000                      900,000
C and D         1,950,000                     860,000
C and E         1,800,000                     800,000
B,D and E     2,850,000                     1,260,000
C, D and E    2,550,000                     1,160,000

The most desirable feasible combination consists of projects B, D and E as it has the highest NPV.

Comments

Popular posts from this blog

Discuss the UNIDO approach of social-cost benefit analysis

Discuss the Little-Mirrlees approach and point out the differences from UNIDO approach to social-cost benefit analysis.

Discuss the type of information required for market and demand analysis.