What are the different methods of ranking of projects?
Ans. Two approaches are
available for determining which project to accept and which projects to reject
: (i) the method of ranking, and (ii) the method of mathematical
programming.This section discusses the method of ranking ; the following
section discusses the method of mathematical programming.
The method of ranking consists of two steps : (i) Rank all
projects in a decreasing order according to their individual NPV’s, IRR’s or
BCR’s. (ii) Accept project in that order until the capital budget is exhausted.
The method of ranking, originally proposed by Joel Dean is seriously impaired by
two problems: (i) conflict in ranking as per discounted cash flow criteria, and
(ii)project indivisibility.
Conflict in Ranking
In a given set of projects, preference ranking tends to differ
from one criterion to another. For example, NPV and IRR criteria may yield
different preference rankings. Likewise, there may be a discrepancy between the
preference rankings of NPV and BCR (benefit cost ratio) criteria. When
preference rankings differ, the set of projects selected as per one criterion tends
to differ from the set of projects selected as per some other criterion. This
may be illustrated by an example. Consider a set of five projects, A, B, C, D,
and E, for which the investment
outlay, expected annual cash flow, and project life are as shown
below:
Project
Investment outlay
Expected annual Project
life
cash flow
(Rs)
(Rs)
(Years)
A
10,000
4,000 12
B 25,000 10,000 4
C
30,000
6,000 20
D
38,000 12,000 16
E
35,000
12,000 9
The NPV, IRR and BCR for the five projects and the ranking along
these dimensions
are shown below
NPV, IRR and BCR for the
Five Projects
Project NPV NPV IRR IRR BCR
BCR
(Rs)
Ranking (Per cent) Ranking Ranking
A
14,776 4 39
1 2.48 1
B 5,370
5 22 4 1.21 5
C 14,814 3 19 5 1.49 4
D 45,688 1 30 2 2.20 2
E 28,936 2 29 3 1.83
3
It is clear that in the above case the three criteria rank the
projects differently. If there is no capital rationing, all the projects would
be accepted under all the three criteria though internal ranking may differ
across criteria. However, if the funds available are limited, the set of
projects accepted would depend on the criterion adopted. What causes ranking
conflicts? Ranking conflicts are traceable to differing assumptions made about
the rate of return at which intermediate cash flows are re-invested.
Project Indivisibility
A problem in choosing the capital budget on the basis of
individual ranking arises because of indivisibility of capital expenditure
projects. To illustrate, consider the following set of projects (ranked
according to their NPV) being evaluated by a firm which has a capital budget
constraint of Rs. 2,500, 000.
Project
Outlay NPV
Rs.
Rs.
A
1,500,000
400,000
B 1,000,000 350,000
C
800,000
300,000
D
700,000 300,000
E
600,000
250,000
If the selection is based on individual NPV ranking, projects A
and B would be included in the capital budget- these projects exhaust the
capital budget. A cursory examination, however, would suggest that it is more
desirable to select projectsB, C, and D. These three projects can be
accommodated within the capital budget of Rs. 2,500,000, and have a combined NPV of Rs. 850,000, which is greater than the
combined NPV of projects A and B.
Feasible Combinations Approach
The above example suggests that the following procedure may be
used for selecting the set of investments under capital rationing. 1. Define
all combinations of projects which are feasible, given the capital budget restriction
and project interdependencies.
2. Choose the feasible combination that has the highest NPV. To
illustrate this procedure, consider the following projects that are being
evaluated by a firm which has a capital budget constraint of Rs. 3,000,000.
Project Outlay NPV
Rs.
Rs.
A 1,800,000 750,000
B 1,500,000
600,000
C 1,200,000
500,000
D 750,000 360,000
E 600,000 300,000
Projects B and C are mutually exclusive. Other projects are
independent Given the above information the feasible combinations and their NPV
are shown below:
Feasible Outlay NPV combination
Rs.
Rs.
A 1,800,000 750,000
B 1,500,000 600,000
C 1,200,000
500,000
D 750,000 360,000
E 600,000
300,000
A and C 3,000,000 1,250,000
A and D 2,550,000 1,110,000
A and E 2,400,000 1,050,000
B and D 2,250,000 960,000
B and E 2,100,000 900,000
C and D 1,950,000 860,000
C and E 1,800,000 800,000
B,D and E 2,850,000 1,260,000
C, D and E 2,550,000 1,160,000
The most desirable feasible combination consists of projects B, D
and E as it has the highest NPV.
Comments
Post a Comment